CHICAGO (WLS) — IDOT says its on track to wrap up the Kennedy Expressway rehabilitation project by this Thanksgiving.
So far, IDOT has delivered on their promise to relieve traffic for some drivers on the North and Northwest Sides.
ABC7 Chicago is now streaming 24/7. Click here to watch
On Wednesday, IDOT reopened three major outbound Kennedy exit ramps: Kimball Avenue, Addison Street and Pulaski Road/Irving Park Road (Illinois 19).
Meaning, all lanes fully reopened from Addison Street to Pulaski Road.
The Kimball Avenue ramp to outbound Kennedy was closed on Tuesday night, IDOT said. It is expected to reopen in approximately three weeks.
The outbound Kennedy ramp to Addison Street was also closed, it is anticipated to reopen in approximately three weeks.
Last week, all I-90/94 lanes north of Addison Street are reopened.
I-TEAM | Detour for Kennedy Expressway construction has trucks barreling down residential street on NW Side
IDOT said the reversible express lanes will remain open in the outbound direction. The reversible mid-gate entrance and exits will remain closed.
Current ramp closures on the outbound Kennedy include:
-Augusta Boulevard/Milwaukee Avenue: expected to reopen mid-October.
-North Avenue (Illinois 64): expected to reopen early September.
-Armitage Avene: expected to reopen early September.
-Fullerton Avenue to outbound Kennedy and the slip ramp portion to Western Avenue, anticipated to reopen mid-September.
-Diversey Avenue: to reopen in mid-September.
According to IDOT, the outbound Kennedy project is progressing as planned and is expected to be finished by Thanksgiving, at which point all lanes and ramps will reopen, and the express lanes will return to their regular function.