Trump administration reveals latest plans in White House renovations

The Trump administration has unveiled ambitious plans for a significant renovation of the White House grounds.

Released on Friday, the new blueprint details plans for an underground security facility designed to screen visitors to the iconic Washington, D.C., site.

The proposed project involves constructing a large, 33,000-square-foot underground center located beneath Sherman Park, which lies just southeast of the White House and south of the Treasury Building.

Construction could begin as early as August, with the goal of completing the facility by July 2028, six months before the end of Trump’s term in office.

The overview of the project states, “The permanent facility will bolster campus security and improve the visitor experience.”

Historically, tourists and visitors have been screened in temporary trailer setups before being allowed entry through the East Wing entrance.

But October saw the East Wing flattened as Trump cleared the way for a $400 million private ballroom, a move that sparked fierce controversy.

Today, visitors wait in line by Lafayette Park to get in, just steps across Pennsylvania Avenue from the White House.

The plan envisions 33,000 sq ft underground center beneath Sherman Park, just southeast of the White House and south of the Treasury

On Friday, the Trump administration revealed plans for an underground security hub to screen visitors (pictured: White House is seen Feb. 24, 2026)

The preliminary agenda is the latest step in the Trump administration's sweeping overhaul of the White House grounds

The preliminary agenda is the latest step in the Trump administration’s sweeping overhaul of the White House grounds

Under the new plans, visitors will begin to enter the facility via an exterior ramp leading to a sunken plaza, where tickets and identification will be verified. 

The 5,000 sq ft recessed entry will act as a gathering area for visitors, allowing them to queue along the ramp instead of crowding the adjacent 15th Street sidewalk. 

Per the White House agenda, the facility will be equipped with the necessary security systems, technology and support space to satisfy US Secret Service (USSS) requirements for handling large crowds of visitors at tours and events. 

Once fully in the facility, visitors will go through two security steps: pre-screening and primary screening.

The seven-lane primary screening area is intended to cut down wait times while handling current security procedures and easily adapting to future upgrades.   

After passing through security, guests will move through a tunnel lined with displays from the White House tour office and the Executive Office of the President. 

From there, visitors will take an elevator up out of the underground facility and exit inside the secure area of the White House complex, where they’ll begin their visit. 

A single escalator will return visitors to ground level north of the secure fence along East Executive Avenue. 

Visitors will begin to enter the facility via an exterior ramp leading to a sunken plaza, where tickets and identification will be verified

Visitors will begin to enter the facility via an exterior ramp leading to a sunken plaza, where tickets and identification will be verified

Construction could begin as early as August, with the White House determined to have the facility ready by July 2028

Construction could begin as early as August, with the White House determined to have the facility ready by July 2028

The plan envisions 33,000 sq ft underground center beneath Sherman Park, just southeast of the White House and south of the Treasury

The plan envisions 33,000 sq ft underground center beneath Sherman Park, just southeast of the White House and south of the Treasury 

According to the outline, the monument of Union General William Tecumseh Sherman at the heart of Sherman Park will stay put. 

‘Landscape restoration, including new tree plantings, will be provided within all impacted zones to reinstate and enhance the park’s character,’ the agenda reads. 

Placing the screening center underground will ‘reduce visual impact’ and avoid conflicts with infrastructure in the southeast corner of the park, according to the plans.

Also highlighted in the agenda were environmental considerations, with the site selection ‘carefully considered to ensure new elements blend with the park’s historic fabric and the city’s architectural character.’

‘The project has been designed to minimize cultural, visual, and environmental impacts to the extent practicable,’ the plans read.

‘While approximately six trees would be removed, these would be replaced with suitable native species,’ it added. 

The Executive Office of the President, the USSS and the National Park Service – which manages the White House grounds – are all collaborating on the ambitious plans. 

The National Capital Planning Commission, responsible for federal construction, is set to review the proposal on April 2.

The agenda also includes discussion and a final vote on Trump’s proposal to erect a 90,000-square-foot building featuring his massive ballroom where the East Wing once stood. 

October saw the East Wing demolished as Trump cleared the way for a $250 million private ballroom in his temporary home

October saw the East Wing demolished as Trump cleared the way for a $250 million private ballroom in his temporary home

The site selection was 'carefully considered to ensure new elements blend with the park's historic fabric and the city's architectural character'

The site selection was ‘carefully considered to ensure new elements blend with the park’s historic fabric and the city’s architectural character’

Last month, Trump installed his 26-year-old executive assistant Chamberlain Harris (pictured) as the latest member of the panel meant to oversee his White House ballroom project

Last month, Trump installed his 26-year-old executive assistant Chamberlain Harris (pictured) as the latest member of the panel meant to oversee his White House ballroom project

Last month, Trump installed his 26-year-old executive assistant as the latest member of the panel meant to oversee his controversial White House ballroom project.

Chamberlain Harris, deputy director of Oval Office operations, was sworn in to the Commission of Fine Arts, one of two bodies required to approve the plan. 

Harris didn’t study art or architecture in college, instead majoring in political science at the University of Albany, SUNY, with minors in communications and economics, according to a Washington Post report on the pick.

Her appointment came after Trump hurriedly named seven members to the commission in January, having fired everyone remaining on the panel the previous October.

The National Trust for Historic Preservation is suing the president, arguing he should have allowed the ballroom project to go through the CFA and the National Capital Planning Commission before demolishing the East Wing.

A ruling is expected soon, with the Washington Post reporting that the federal judge keyed in on private donations being used to fund the estimated $400 million project, as a way to bypass Congressional authorization.

In January, the architect helming the design for Trump’s ballroom project revealed new plans for a West Wing expansion.

You May Also Like

Lindsay Clancy’s Lawyers Say She Won’t Testify at Ex-Husband’s Hearing

Lindsay Clancy’s lawyer has rejected claims that she plans to testify in…

Patrick Stewart, Star Trek and X-Men Actor, Dies at Age 86

Star Trek legend Sir Patrick Stewart has died at the age of…

UK Households Could Be £1,050 Worse Off by 2029, Think Tank Warns

Working-age households could be around £1,000 worse off over the next two…

Katie Holmes, 47, Poses With 39-Year-Old Boyfriend on Red Carpet

Katie Holmes looked completely smitten as she cuddled up to her younger…

Obama Calls Ilhan Omar ‘Sham Marriage’ Probe Appalling, Though It Began Under His Administration

WASHINGTON — Former President Barack Obama has sharply criticized the Trump administration’s…

George Michael’s Iconic Faith Guitar Set to Sell for £120,000

A guitar played by George Michael in the video for his hit…

New Investigation Opened Into Democratic Rep. Mary Peltola of Alaska

Alaska Republican Gov. Mike Dunleavy has ordered an investigation into Democratic Senate…

DA Says Lindsay Clancy Murder Charges Should Not Be Dismissed

Prosecutors are asking a judge to deny Lindsay Clancy’s request to dismiss…

UK Defence Secretary Healey risks PM’s bid to ease Brexit splits

Andy Burnham’s attempt to impose Cabinet discipline over Brexit tensions suffered a…

Rachel Reeves U-Turns on Welfare Cuts Hours After Pledging to Reduce Benefits Bill

John Healey was forced into an embarrassing retreat over welfare spending on…

Hollywood Sign Neighbors Say Fear Has Taken Over Their Lives

Residents living near the iconic Hollywood sign say they fear a wildfire…

Netanyahu Bloc Leads Opposition as Israel Vote Count Continues

Prime Minister Benjamin Netanyahu’s right-wing and religious coalition bloc remained ahead of…