Ofgem Crackdown on Unviable Data Centres to Free Grid Capacity - Internewscast Journal
Ofgem Crackdown on Unviable Data Centres to Free Grid Capacity

Britain’s energy regulator is considering a refundable upfront “commitment fee” for major data centre developments, in a move aimed at easing pressure on the country’s electricity grid.

Ofgem said the proposal is designed to make sure scarce grid capacity is reserved for schemes that are genuinely “ready and able to connect”, while addressing concerns that speculative data centre projects are clogging up Britain’s electricity connections queue.

The regulator’s intervention comes amid growing unease that some developers may be seeking to profit from rising land values rather than move forward with viable projects.

Under the plans, the fee would be paid when a developer receives a connection offer and would be refunded once the data centre is switched on, Ofgem said.

However, if a developer gives up its place in the queue, the payment would not be returned.

Proposal: Ofgem is considering a new upfront fee on developers for large data centre projects

Proposal: Ofgem is considering a new upfront fee on developers for large data centre projects

The proposed commitment fee would fall between £237,500 and £712,500 per megawatt, representing roughly 2.5 per cent to 7.5 per cent of average project costs.

In addition to the potential charge, Ofgem said it is consulting on the introduction of “queue management milestones” for large data centre projects.

Data centre developers would need to demonstrate ‘tangible progress’ through evidence including financial capability, commercial maturity and procurement activity if they wished to retain their place in the queue. 

The regulator said: ‘Ofgem is concerned that a significant number of projects in the queue may not ultimately proceed, potentially delaying viable developments and creating misleading signals about future network investment needs.’ 

Ofgem said there were 315 data centres currently queueing to connect up, representing 73 gigawatt (GW) of demand. This was almost 30GW above the entire country’s peak energy demand of 45GW.  

Eleanor Warburton, Ofgem’s director for energy system design and development, said: ‘Britain’s electricity demand connections queue has more than tripled in size in less than a year, and consumers should not bear the risks created by speculative projects taking up space in the system.

‘The connections system must work for consumers and for the projects that are ready to invest, build and connect. Where speculative projects take up space in the queue, they can delay other schemes and create uncertainty about future network needs.’

What are data centres?   

Data centres are buildings that contain information technology equipment. They are used to house, connect, and operate computer systems like servers for data storage, processing or distribution. 

They are important for cloud computing and artificial intelligence (AI). In September 2024, the government designated data centres as critical national infrastructure.

Data centres are the nervous system of AI tools like chatbots but they have increasingly sizeable energy requirements as their usage and capability increases. 

Britain has around 450 large data centres, with London holding more capacity than the rest of Britain combined. 

The Slough Trading Estate has 30 data centres in its one square mile, which is the highest concentration in Europe.

Owned and maintained by a variety of global companies, the data centres on the Slough Trading Estate store, process and transmit digital information for dozens of clients, including Amazon, Google and Microsoft. Locals have complained that the data centres make a low humming noise which they can hear at night. 

In February, Ofgem said there had been a ‘surge in demand’ for connection applications between November 2024 and June 2025, with a significant number coming from data centres. 

Again in February, Ofgem said there were 140 proposed data centres with energy demands of 50GW. 

The number of proposed data centres and energy demand levels has since increased, Ofgem said today. Applications for new power connections have more than tripled in less than a year. 

In July 2025, the National Energy Systems Operator estimated that data centres used around 2 per cent of all electricity in Britain. Most data centre energy powers the server computing directly, with around a third used for cooling. 

Government emissions forecasts for AI data centres were revised up by around 100-fold this month after officials acknowledged they had significantly underestimated the sector’s future energy demands. 

DIY INVESTING PLATFORMS

Easy investing and ready-made portfolios

AJ Bell

Easy investing and ready-made portfolios

AJ Bell

Easy investing and ready-made portfolios

Free fund dealing and investment ideas

Hargreaves Lansdown

Free fund dealing and investment ideas

Hargreaves Lansdown

Free fund dealing and investment ideas

Flat-fee investing from £4.99 per month

interactive investor

Flat-fee investing from £4.99 per month

interactive investor

Flat-fee investing from £4.99 per month

Investing Isa now free on basic plan

Freetrade

Investing Isa now free on basic plan

Freetrade

Investing Isa now free on basic plan

Free share dealing and no account fee

Trading 212

Free share dealing and no account fee

Trading 212

Free share dealing and no account fee

Affiliate links: If you take out a product This is Money may earn a commission. These deals are chosen by our editorial team, as we think they are worth highlighting. This does not affect our editorial independence.

Compare the best investing account for you

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

Fed Rate Decision Today: Why a Hold Is Likely, What to Watch

Topline The Federal Reserve is widely expected to leave interest rates untouched…

2026 MLB Trade Deadline Nears as League-Wide Parity Shapes Buyers and Sellers

SACRAMENTO, CA: San Francisco Giants hitter Luis Arraez tosses his bat toward…

Visa Cuts 2,600 Jobs as AI and Cost Pressures Reshape Plans

Visa is preparing to eliminate around 2,600 positions, a reduction equal to…

How Founders Can Avoid Losing Six Figures in a Business Sale

Opinions expressed by Entrepreneur contributors are their own. Key Takeaways For many…

Tax-Free Investing: Pension vs ISA Rules to Cut Your Bill

For investors, keeping hold of more of the gains they have worked…