The Brooklyn building next to the one that collapsed and killed eight people last week will be demolished after city officials determined that extensive damage has made it unsafe.
The Department of Buildings announced Wednesday that a multi-agency review of the structural integrity of 1323 Flatbush Ave. found the property to be severely compromised. Officials have ordered its demolition.
“Unfortunately, allowing workers into the building to perform the heavy-duty shoring required to stabilize it would put those workers at risk,” city Buildings Commissioner Ahmed Tigani said.
“Given the building’s dangerous condition and the need to ensure that no one else is injured, a controlled, safe demolition is the only available option,” Tigani said.
The collapse of 1321 Flatbush Ave. on Nov. 11 left the neighboring building unstable. Its condition has deteriorated even further since then because of exposure to the weather.
Eight people — six adults and two children — were killed in the collapse, while 20 others were injured.
Before demolition crews can begin tearing down the building, city contractors must install support shoring at 1325 Flatbush Ave., where full vacate orders remain in effect.
In the meantime, displaced tenants are staying in hotels arranged by the city Department of Housing Preservation and Development and the American Red Cross through the end of November.
Because of the building’s compromised structure and extensive asbestos contamination, the tenants will not be allowed to return to their apartments to retrieve their belongings before demolition begins.
RELATED: Meet the Kids of Amy and Ben Brown after their Divorce
City inspectors approved deep excavation plans at a neighboring site in March, and many residents fear the work may have contributed to the fatal collapse.

The Department of Buildings signed off on plans to excavate the lot at 2625 Bedford Ave., where a developer planned to build a three-story, 25,000-square-foot mixed-use property.
Although records obtained by The Post detail sophisticated bracing along portions of the site — including the backyard of 1321 Flatbush Ave. — they show that heavy-duty reinforcement was missing directly alongside the building.
Warning signs appeared almost immediately.
An inspection report submitted to the city by the developers’ own contractors noted visible cracks along the north facade of 1321 Flatbush Ave. and described the building as severely compromised.
City officials stopped the construction that same month.
After the deadly collapse, the Buildings Department issued immediate vacate orders for neighboring properties at 1325 and 1327 Flatbush Ave.
The agency is now investigating six separate developers connected to the project at 2625 Bedford Ave.